What does a Gantt chart primarily depict?

  1. Employee performance statistics over time

  2. Project tasks against a timeline

  3. Financial budgets for various projects

  4. Resource allocation in a project

The correct answer is: Project tasks against a timeline

A Gantt chart primarily depicts project tasks against a timeline, which makes it an essential tool for project management. It visually represents the start and end dates of various tasks involved in a project, allowing managers and team members to see how tasks overlap and the overall timeline of the project. This visual tool can help track progress, deadlines, and dependencies between tasks, ensuring that the project stays on schedule and that resources are effectively allocated over time. By showing tasks along a horizontal timeline, Gantt charts facilitate communication among team members and stakeholders, making it clear which tasks are in progress, which are completed, and what is upcoming. This clear visualization of project tasks in relation to time helps with planning and can be critical for meeting project deadlines.